Tuesday, May 24, 2022

G-DOT UPDATE ON 19 NORTH WIDENING

GDOT contractors, CW Matthews will be shifting the traffic to the outside lanes on SR 3 mainline on Sunday, June 6th, 2022 in order to switch to the next stage of the plans which includes constructing the concrete median. This will take place at 7 pm Sunday night and go until 7 am Monday morning June 6, 2022. Message boards have been placed warning about the new traffic pattern.

This project widens the 4-lanes of US 19 to make them 12'. It also proposes to add a raised median. The project begins at the intersection of US 19 and County Road and ends at the intersection of US 19 and Atwater Road, approximately 2 miles north of Thomaston. Also, as part of this project, Delray road will be realigned to intersect with US 19 and Jimmerson Road. 

A signal will be added at this location.